South Redding I-5 6-lane

Description: Near Redding, from north of Smith Road overcrossing to north of Route 5/299 separation. Add a median lane and widen structures.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
 
County/State Route Shasta 5
Postmile Begin/End R  10.5 R  17.5
 
County/State Route Shasta 5
Postmile Begin/End 10.5 17.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      541  
Lane Miles Added (Mixed)      9.5  
Peak Period Time Savings (minutes)      3230  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans District 2 Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Design (PS&E) Phase
Caltrans District 2 Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Right of Way Phase
Caltrans District 2 Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Construction Phase
Caltrans District 2 Eric Orr 530-225-3466   eric.orr@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
CMIA
$22,500 $-1,597 $20,903
Non-bond Funding
State/Federal*
$1,755 $0 $1,755
Non Budgeted ETC
$0 $0 $0
 
Total**** $24,255 $-1,597 $22,658

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,195 $0 $1,195 $933
Design(PS&E)
$510 $0 $510 $842
Right of Way
$50 $0 $50 $30
Construction
$22,500 $-1,597 $20,903 $20,604
 
Total* $24,255 $-1,597 $22,658 $22,409

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2008 

05/13/2010 
 

 
07/01/2008 

05/13/2010 
100  07/01/2008 

05/13/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/14/2010 

11/15/2010 
 

 
05/14/2010 

11/15/2010 
100  05/14/2010 

12/15/2010 


-1 
Begin Right of Way Phase

End Right of Way Phase
05/14/2010 

10/19/2010 
 

 
05/14/2010 

10/19/2010 
100  05/14/2010 

09/30/2010 


Begin Construction Phase

End Construction Phase
02/17/2010 

11/15/2012 
06/01/2011 

 
06/17/2011 

11/15/2012 
100  05/09/2011 

02/01/2013 


-3 
Begin Closeout Phase

End Closeout Phase
11/16/2012 

11/15/2013 
 

 
11/16/2012 

11/15/2013 
100  02/02/2013 

08/17/2016 
-3 

-34 
Corridor System Management Plan
Adoption Date 06/01/2008    06/01/2008  05/01/2008 
Implementation Date 01/01/2007    01/01/2007  06/23/2008  -18 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 541
Lane Miles Added (Mixed) 9.5
Peak Period Time Savings (minutes) 3230

Bond Funding Cost
Adopted:
$22,500,000
Current Approved:
$20,903,000
Actual Expenditures:
$20,603,000

 

Status as of December 31, 2023.